2007 DRAINAGE
|
Streets Name |
Footage |
Cost |
|
Del Bello Rd, Lira & Tammy |
2,505 |
$ 5,010 |
|
Wilson North |
2,390 |
$ 4,780 |
|
Wilson South |
2,200 |
$ 4,400 |
|
McCoy North |
3,530 |
$ 7,060 |
|
School Rd. |
1,730 |
$ 3,460 |
|
SubTotal |
|
$
24,710 |
|
Driveways Reset (approx) |
25 |
$ 11,250 |
|
Street Crossings Reset (approx) |
3 |
$ 3,000 |
|
Total |
|
$ 38,960
|
2007 SPECIAL ROADS PROJECT |
|
Street Name |
Stone |
Cost |
Oil |
Cost2 |
Asphalt |
Cost3 |
Footage |
Total Cost |
|
Wilson (N) |
405 Tons |
5,637.60 |
2230 Gals |
3,166.60 |
640 Tons |
28,160.00 |
1695 |
$ 36,964.20 |
|
Wilson(S) |
120 Tons |
1,670.40 |
660 Gals |
937.20 |
200 Tons |
8,800.00 |
500 |
$ 11,407.60 |
|
McCoy |
285 Tons |
3,967.20 |
1555 Gals |
2,208.10 |
470 Tons |
20,680.00 |
1180 |
$ 26,855.30 |
|
Mustang |
0 |
0.00 |
2250 |
3,366.30 |
648 Tons |
28,512.00 |
|
$ 31,878.30 |
| |
|
|
|
|
|
SUB TOTAL |
|
$107,105.40 |
|
HUD |
|
0.00 |
|
0.00 |
|
0.00 |
|
$ (13,149.30) |
| |
|
|
|
|
|
TOTAL |
|
$ 93,956.10 |
|
*Total cost is $31,878.30 - HUD $13,149.30=
$18,729.00 MANVEL COST FOR
MUSTANG |
December Monthly Report
Completed Projects
-
Louisiana Street Bridge is now open to the
public. With help from Brazoria Drainage
Precinct 3 work on the Louisiana Street Bridge
completed in 14 working days. The following repairs
were completed:
- 7 caps
- 141 stringers
- 170 decking
boards
- 15 pylons
-
Clark Bridge is now open to the public. The
work was completed in 18 working days with the help
of Precinct 3. The following repairs were performed:
- 19 pylons
- 62 stringers
- 72 decking
boards
- 4 caps
- 20 metals rods
-
Master @ Uzzell on Tuesday November 14, 2006
emergency repairs were performed. With the help of
Brazoria County Road and Bridge Precinct 3 the
repairs were able to be completed in the shortest
possible time. To repair the bridge we remove 2 -
36" tin horns and replaced them with 14 concrete
culverts (36" x 6') and headers walls were built on
both sides of the road.
-
Water Plant on Corporate Drive (Well #1) was
serviced to increase the flow from 33 gpm to 80 gpm:
-
Installed a new
Aqua duty pump
-
Installed duplex
pump control panel with plugs
-
Installed Airite
610 tank for air control system
-
Well was jetted
with air
-
Water Plant on School Road (Well #2) after
investigating reports of low water pressure it we
found that the incoming power supply (supplied by
CenterPoint Energy) lost power and there was also a
blown fuse. CenterPoint restored power and within 30
minutes of the repair water pressure was back to
normal. We also installed a junction box and 1/2"
conduit to help with weather-proofing and for the
Airite 610 tank for air control system.
-
A
new fire hydrant was installed next on Highway 6
next to the Naked Rib Restaurant.
Upcoming Projects
|
|
 |
|